About these figures
This page answers how much cement, sand and aggregate goes into one cubic metre of concrete for each nominal grade, and how much cement you need for brickwork mortar and wall plaster. Every figure comes from the same method as the Kitlantis construction calculators, so it agrees with the Concrete, Brick and Plaster calculators. Below the charts, the Concrete Calculator works out the materials for your own slab, footing or column.
How to use it
- Find your grade or mix in the tables: M20 is common for house slabs and columns, and 1 : 6 mortar for inside brick walls.
- Multiply the per m³ figure by your volume in cubic metres, or use the per 100 cft column.
- Add about 5% for wastage and round the cement up to whole bags.
- For an exact size, enter it in the Concrete Calculator below the charts.
Example
A 3 m³ slab in M20 needs about 3 × 8.1 = 24.2 bags of cement; with 5% wastage that is 25.4, so order 26 bags. It also needs about 1.26 m³ of sand and 2.52 m³ of aggregate before wastage.
How the numbers are worked out
Cement, sand and aggregate are measured dry, and they lose about a third of their volume once water is added and the concrete is compacted. So 1 m³ of finished concrete needs about 1.54 m³ of dry materials, split in the ratio of the mix. M20 is 1 : 1.5 : 3, which is 5.5 parts, so the cement is 1.54 ÷ 5.5 = 0.28 m³. Loose cement weighs about 1,440 kg per m³, which gives 403 kg, or about 8.1 bags of 50 kg. Mortar uses a factor of 1.33 and plaster 1.27, since they have no coarse aggregate.
Nominal mix or design mix
The M grades here are nominal mixes, the fixed ratios given in IS 456 for smaller works. Larger structural jobs at M20 and above are usually built with a design mix tested for the actual sand and aggregate, which can need less cement for the same strength. Damp sand also bulks up, so measuring it by volume can leave a mix short of sand. Use these figures to estimate and order, and follow your engineer’s mix where there is one.
Questions people ask
How many cement bags are needed for 1 m³ of M20 concrete?
About 8.1 bags of 50 kg (403 kg), using the 1 : 1.5 : 3 nominal mix and a dry volume factor of 1.54.
How many bags of cement make 1 cubic metre?
One cubic metre of loose cement weighs about 1,440 kg, which is 28.8 bags of 50 kg. One bag takes up about 0.035 m³, or 1.23 cft.
How much cement is needed for 100 sq ft of plaster?
About 0.82 bags for 12 mm plaster in 1 : 4, or 0.58 bags in 1 : 6, before wastage.
Do these figures include wastage?
No. They are for exact volumes. Add about 5% for concrete and plaster, and round up to whole bags when you order.